Crow's Nest Rise Remedial Options

Closed for feedback

About the Crow's Nest Rise Remedial Options

This consultation closed on 18 March 2019. Thank you for having your say.

We received 79 online submissions on the Crows Nest Rise remedial options.

Key themes from the feedback

  • 85 per cent preferred the slips were repaired and the walkway reopened.
  • 9 per cent preferred Slip B (the stairs) were repaired and the remaining walkway realigned to go around the road.
  • 4 per cent preferred the walkway was realigned to follow the road access, and no repairs were undertaken.

Next steps

We are currently working on the design and consents to reopen the walkway by the end of the year.

Planting will be undertaken on the slip areas in May to June 2020, when the weather is more suitable.

Slip A: Bournemouth Terrace

This site is stabilised enough for the walkway to be realigned further away from the cliff.

A new fence will be installed.

Construction is expected to be complete by December 2019.

Slip B: Montrose Terrace stairs

A new staircase will be installed over the existing damaged ones.

Construction is expected to be complete by Christmas 2019.