Industrial cooling tower water systems

He pourewa pūnaha whakamātao wai ahumahi

​What are industrial cooling tower water systems?

Industrial cooling tower water systems are cooling devices used in an industrial process.

These systems are not:

  • part of a building as defined in the Building Act 2004
  • included in a compliance schedule.

Register an industrial cooling tower water system

If you own an industrial cooling water system, you need to:

  • register it with us by 1 July each year
  • let us know if the system is decommissioned (within a month of this occurring)
  • let us know if there is a change in ownership (within a month of this occurring)
  • comply with the maintenance, chemical dosing and testing requirements outlined in the Property Maintenance and Nuisance Bylaw.

You should know

If incorrectly maintained, industrial water cooling systems can spread Legionnaire's disease.

If you don't comply with the Property Maintenance and Nuisance Bylaw, we may prosecute you under the Local Government Act 2002. Fines are up to $20,000.

​Registration fee

Read fee table.
Service Fee
Industrial cooling tower - Registration$171
Industrial cooling tower - Renewal$109

​How to register an industrial cooling tower water system

 By email

Email the completed AC3406 Industrial cooling tower water system registration form to the Cooling towers team.

 In person

​Download and complete the registration form.

Bring the completed AC3406 Industrial cooling tower water system registration form to the service centres closest to you and pay by:

  • cash
  • cheque
  • Eftpos
  • MasterCard or Visa  (A convenience fee of 1.75 per cent of your payment amount applies).

 By post

​Send the completed AC3406 Industrial cooling tower water system registration form and cheque payment to:

CCC team (Cooling towers)
Central Building Control
Auckland Council
Victoria Street
Auckland 1142
Private Bag 92300

 Related topics

 

 

Apply to amend a compliance schedulehttps://www.aucklandcouncil.govt.nz/building-and-consents/commercial-building-systems/Pages/apply-amend-compliance-schedule.aspxApply to amend a compliance scheduleFind out when you should apply for an amendment to the existing compliance schedule and how you can do this.aspx
Apply for a compliance schedulehttps://www.aucklandcouncil.govt.nz/building-and-consents/commercial-building-systems/Pages/apply-for-compliance-schedule.aspxApply for a compliance scheduleFind out what you need before you apply and how to apply for a compliance schedule. aspx
Building warrant of fitness (BWOF)https://www.aucklandcouncil.govt.nz/building-and-consents/commercial-building-systems/Pages/building-warrant-of-fitness.aspxBuilding warrant of fitness (BWOF)You will need to get and display an annual certificate, a building warrant of fitness (BWOF), to confirm that systems within your building are functional and meet compliance schedule requirements. aspx
Certify the specified systems in your buildinghttps://www.aucklandcouncil.govt.nz/building-and-consents/commercial-building-systems/Pages/certify-specified-systems-building.aspxCertify the specified systems in your buildingWhen, how and why you need to certify the systems within a building to ensure it is safe for public use and its occupants. We issue compliance schedules to confirm that systems are fully functional.aspx