Skip to main content

Te kaupapa mahi ki te whakahōu i te Muriwai o Tāmaki Herenga Waka

Port of Auckland outfall upgrade project

This $40m project will significantly upgrade the downtown port area stormwater system, increasing its capacity to deal with flooding. The work will also extend the life of existing infrastructure and provide vital infrastructure for future growth.

About the stormwater improvement

The unexpected collapse of the Ōrākei main sewer in September 2023 caused some delays. We commissioned and installed a new stormwater pipe in early December 2023.

The stormwater pipe runs from the south-eastern end of Quay Street (east of Spark Arena and west of a row of shops and services at 8–14 Quay Street), and extends across the Port of Auckland site.

The new pipeline allows us to turn off the existing 80-year-old culvert while we investigate and restore it.

We expect to begin repairs to the culvert in late March 2024 and complete the work by November 2024, when we will reconnect the pipeline to the outfall.

This will provide additional capacity in the stormwater network.

Traffic management on Quay Street

Every effort is being made to ensure that traffic on this busy commuter route can continue to flow without significant interruption. 

All lanes will continue to be open:

  • two general lanes travelling east
  • two-way cycle lanes
  • two general lanes travelling west
  • a bus-only lane from 6am to 10am travelling west.

Traffic lanes will be shifted

For a short 200m section on Quay Street, all traffic lanes have been moved slightly to the north to avoid construction works.

A section of the central median strip will be temporarily removed to allow this shifting of traffic. 

A traffic management plan is in place with barriers and signage.

Access to retail outlets

There will continue to be access to the retail outlets at 8–14 Quay Street, with slightly altered areas for entry and exits clearly marked.

Working hours on the project

Working hours on the site are from 7.30am to 6pm Monday to Saturday. 

Occasional work outside these hours may be required, but we will notify affected residents if this is necessary.

Noise and truck movements will be kept within acceptable limits.

Tree removal and replanting

Two pōhutukawa trees on the roadside along the triangle of grass at 16 Quay Street have been carefully removed and will be looked after for the duration of the project.

After the project finishes, they will be replanted as close to possible to their original positions.

More information

Email us with any questions or to go on the mailing list for regular updates:

portsofaucklandoutfallHW@aucklandcouncil.govt.nz

For enquiries during construction, contact McConnell Dowell:

0508 623 266

Related topics