Extension of time to commence building work

From the date your building consent was issued, you have 12 months to start work. After 24 months, we must decide whether or not to issue the Code Compliance Certificate.

When to apply for an extension of time

Your consent may lapse if you cannot start building work within 12 months.

To avoid your consent lapsing, you need to apply for an extension of time before the specified time frame is reached.

Work not started

If you have not started work or we have not done any inspections within 12 months of issuing your consent, we will send you a letter asking if you intend to proceed.

If you want to proceed but need more time, apply for an extension of time.

Our tip

If you don't apply for an extension of time before your consent lapses, you will need to apply for a new building consent to complete your project.

Application fees for extension of time

* Fees are indicative pricing only

Read fee table.
Service Fee
Extension of time to commence building work under a building consent - Fixed Fee (non-refundable, no additional charges) $157
Lapsing of building consent - Base fee (non-refundable, additional charges may apply) $175

​How to apply for an extension of time

 Online

​Apply now

We only accept online applications for this service. If you are unable to apply digitally, visit one of our service centres for assistance in making your online application.

Call us on 09 301 0101 to speak with our building and planning help desk if you have questions regarding your application.

What happens next

The team leader or senior inspector will consider your application and after reviewing your building consent file, will make a decision. The decision will depend on whether there have been any changes to the Building Code.

 

 Related topics

 

 

Pay a consent invoicehttps://www.aucklandcouncil.govt.nz/building-and-consents/tracking-paying-consent-application/Pages/pay-consent-invoice.aspxPay a consent invoiceFind out how to pay a building consent, resource consent or regulatory engineering invoice.aspxBuilding consents
Request a consent fee refundhttps://www.aucklandcouncil.govt.nz/building-and-consents/tracking-paying-consent-application/Pages/request-consent-fee-refund.aspxRequest a consent fee refundIf you believe that we owe you money related to your building consent or building inspections, you can request a refund. Find out how here.aspxBuilding and consents
Apply for an amendment (major variation) to your building consenthttps://www.aucklandcouncil.govt.nz/building-and-consents/building-consents/making-change-building-consent/Pages/apply-for-amendment.aspxApply for an amendment (major variation) to your building consentIf you are making changes to a building consent, find out if you need to submit an amendment. aspxBuilding consents
Apply for a minor variation to your building consenthttps://www.aucklandcouncil.govt.nz/building-and-consents/building-consents/making-change-building-consent/Pages/apply-minor-variation-building-consent.aspxApply for a minor variation to your building consentIf you are making changes to a building consent, find out if you need to submit a minor variation.aspxBuilding consents
Change Licensed Building Practitioner (LBP) details for your projecthttps://www.aucklandcouncil.govt.nz/building-and-consents/building-consents/making-change-building-consent/Pages/change-LBP.aspxChange Licensed Building Practitioner (LBP) details for your projectFind out how to change the details of LBPs doing, or supervising, your restricted building work.aspxBuilding and consents