Declare that your building work complies with the Building Code through producer statements (PS)

Whakapuakina kei te hāngai ō mahi hanga whare ki ngā Tikanga Hanga Whare mā roto mai i ngā tākinga kōrero kaitaki kaupapa

132220What is a PS?

A PS is a document issued by a producer statement author - a council-approved expert registered with us.

A PS gives evidence that design or building work complies, or will comply, with the Building Code and helps us make a decision to issue a building consent or a Code Compliance Certificate (CCC).

Some examples of work that may need a producer statement are:

  • foundations
  • waterproofing
  • structural engineering
  • geotechnical engineering.

How to prove that your building work complies with the Building Code through a PS

We may accept the PS alone as evidence that the design or building work complies, or will comply, with the Building Code.

Depending on the nature of your project and the quality assurance systems that the builder has on site, we may require additional information.

Design category producer statements

PS design and design review professionals issue PS1 and PS2 that confirm that they have designed your building work in accordance with New Zealand Building Code (NZBC) requirements.

Producer statement - Design (PS1)

​The design professional who has been engaged to provide a design completes this statement.

Producer statement - Design review (PS2)

​The design professional who has been engaged to provide a design review completes this statement.

Construction category producer statements

Construction producer statements (PS3)

The contractor who has carried out the building work, issues a PS3 to confirm that the building work is in accordance with the consent plans and building code.

Producer statement construction (PS3) Drainage

​The drainlayer who completed the work fills in this statement.

Producer statement construction (PS3) On-site wastewater disposal

​The drainlayer who completed the work fills in this statement.

Producer statement construction (PS3) General construction work

​The person who has undertaken the building work completes this statement.

Producer statement construction (PS3) Plumbing

​The certifying plumber who completed the work fills in this statement.

Producer statement construction (PS3) Tanking

​The applicator who carried out the work, like basement waterproofing, completes this statement.

Producer statement construction (PS3) Waterproofing

​The applicator who carried out the waterproofing work completes this statement.

Producer statement construction (PS3) Balustrades

​The person who has installed the balustrade completes this statement.

Producer statement construction (PS3) Solid fuel heating

​The installer needs completes this statement.

Producer statement construction (PS3) Solar or heat pump water heating

​The person responsible for installing the appliance completes this statement.

Producer statement construction (PS3) Injected wall insulation

​The installer completes this statement.

Producer statement construction (PS3) Emergency lighting

The installer needs to complete this statement.

Producer statement construction (PS3) Interior surface finishes, floor coverings and suspended flexible fabrics

​The person confirming compliance with the consented completes this statement.

Producer statement construction (PS3) Intumescent coatings to structural steel

​The installer completes this statement.

Producer statement construction (PS3) Solar panels

​The person responsible for installing the solar panels completes this statement.

Producer statement construction (PS3) Underfloor heating

​The person who installed the underfloor heating completes this statement.

Construction review producer statements (PS4)

The design professional, who has reviewed the work of the contractor, issues PS4 to confirm that:

  • the building work has been carried out in accordance with the consented plans and Building Code
  • the design professional or us has requested involvement or supervision by a suitably qualified person.

Producer statement construction review (PS4)

​The design professional who has been engaged to observe construction completes this statement.