Apply for a major engineering approval

COVID-19 Alert Level 2 – Building and consents information

Service centres will reopen at Alert Level 2 with necessary health and safety measures in place, including physical distancing and use of the NZ COVID Tracer app.

Building and resource consent applications remain digital only and will only be accepted via the council's website.

To ensure the safety of our staff and customers some of our services remain unavailable at Alert Level 2, including in-person pre-application meetings and drop-in consultations with staff.

Physical inspections and site visits have resumed, but only where appropriate health and safety measures, including social distancing, can be met and are adhered to.

Major engineering approval application fee

Read fee table.
Service Deposit
Approval of engineering works (major) and consent to drainage works - construction of private drains through adjoining premises of works on private land$2500

​How to apply for a major engineering approval

 Online

Engineering approval - major

If you get stuck, consult the online application guide PDF, located towards the end of the When you need an engineering approval page.

 By post

​Send your completed application form and supporting documents to:

Auckland Council

  Private Bag 92300

  Auckland 1142

 In person

​Bring your completed application form and supporting documents to one of our service centres, and pay by:
  • cash
  • Eftpos
  • MasterCard or Visa.

Our tip

At the end of the process, you may need to pay the maintenance bond.

​What happens next

We process the engineering plan approvals within 20 working days unless additional information is required.

We will let you know the decision by email and post.

Phases in the engineering approval process

  1. Assessment and approval of proposal
  2. Construction and inspection
  3. As-built documentation review and completion, and transferring ownership of an asset (like infrastructure).

​Engineering newsletter

Sign up to receive our regulatory engineering newsletter.

 Related topics

 

 

Consider stormwater when buildinghttps://www.aucklandcouncil.govt.nz/building-and-consents/stormwaterConsider stormwater when buildingIf you are doing any sort of development, one of the factors you need to consider is stormwater. Find out what you need to know about stormwater before you begin.aspxStormwater
Development contributionshttps://www.aucklandcouncil.govt.nz/building-and-consents/development-contributionsDevelopment contributionsFind out what development contributions are and the types of projects you may need to pay fees for. Use our tool to estimate your contribution fees.aspxBuilding and consents
Apply for a minor engineering approvalhttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/apply-minor-engineering-approval.aspxApply for a minor engineering approvalFind out how to apply for a minor engineering approval and download the engineering as-built requirements. aspxEngineering
Common access way approvalhttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/common-access-way-approval.aspxCommon access way approvalFind out what a common access way is, and if there are any regional differences in the design and construction processes. It also provides information on how and why we test the common access way.aspxEngineering
Guidelines for engineering approval applicationshttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/guidelines-engineering-approval.aspxGuidelines for engineering approval applicationsRead what you need to apply for an engineering approval and the naming standards to use if you apply online.aspxEngineering
When you need an engineering approvalhttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/when-need-engineering-approval.aspxWhen you need an engineering approvalFind out what type of work might need an engineering approval and how can our development engineers help. aspxEngineering