Apply for a minor engineering approval

Minor engineering approval application fee

Read fee table.
Service Deposit
Approval of engineering works (minor) and common access way$1200

How to apply for a minor engineering approval

Only use this online form for minor works, such as:

  • public stormwater and/or wastewater connections within the site
  • renewal of a public stormwater pipe to the same grade and alignment
  • isolated rehabilitation of existing pipe or manhole
  • raising or lowering a public manhole lid.

We only accept online applications for minor engineering approvals. If you are unable to apply digitally, visit one of our libraries with council services for assistance in making your online application.

See Ways to pay online for information on all payment options.

 

Engineering approval - minor

 

If there is no way to provide digital copies of your plans or documents, visit one of our libraries with council services. Our staff will accept your documents, but it may incur an additional charge to cover the costs involved with us scanning your documents into our digital consent system.

Call us on 09 301 0101 if you have questions regarding your application.

If you get stuck, consult the online application guide PDF, located towards the end of the When you need an engineering approval page. 

Our tip

At the end of the process, you may need to pay the maintenance bond.

What happens next

We aim to process engineering plan approvals within 20 working days. Approval takes longer when additional information is required.

We will let you know the decision by email.

Phases in the engineering approval process

  1. Assessment and approval of proposal
  2. Construction and inspection
  3. As-built documentation review and completion, and transferring ownership of an asset (like infrastructure).

 Related topics

 

 

Consider stormwater when buildinghttps://www.aucklandcouncil.govt.nz/building-and-consents/stormwaterConsider stormwater when buildingIf you are doing any sort of development, one of the factors you need to consider is stormwater. Find out what you need to know about stormwater before you begin.aspxStormwater
Apply for a major engineering approvalhttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/apply-major-engineering-approval.aspxApply for a major engineering approvalFind out how to apply for a major engineering approval and learn the phases of the engineering approval process. aspxEngineering
Common access way approvalhttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/common-access-way-approval.aspxCommon access way approvalFind out what a common access way is, and how to apply. Learn more about how and why we test the common access way.aspxEngineering
Construct drainage over neighbouring propertieshttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/engineering-approval.aspxConstruct drainage over neighbouring propertiesFind out what you can do if you want to construct drainage over neighbouring properties but your neighbours grant or refuse to grant you access approval.aspxEngineering
Guidelines for engineering approval applicationshttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/guidelines-engineering-approval.aspxGuidelines for engineering approval applicationsWhat you need to apply for an engineering approval and the naming standards to use if you apply online.aspxEngineering
When you need an engineering approvalhttps://www.aucklandcouncil.govt.nz/building-and-consents/engineering-approvals/Pages/when-need-engineering-approval.aspxWhen you need an engineering approvalFind out what type of work might need an engineering approval and how can our development engineers help. aspxEngineering